Movie Production Schedules

Complete Timeline & Phase Management

JIO Movie

Production Timeline

Timeline Phase Details
July 14 - Aug 31 Pre-Production Script work, dialogues, composing, location recce
Sep 1 - Oct 18 Shooting 40 days (excluding Sundays/public holidays)
Oct 19 - 22 Break Diwali holidays
Oct 23 - 24 Transfer Footage transfer to edit
Oct 25 - 31 Edit Lock Edit lock for dubbing
Nov 1 - 15 Dubbing Includes 3 days outdoor song shoot & edit
Nov 16 - 19 Sound Sync Add outdoor song
Nov 20 - 24 Final Trimming Lock final footage
Nov 25 Post Start Send to SFX, CG, DI, RR
Nov 26 - Dec 7 Post-Production Background score, DI, SFX, CG, censor
Dec 8 - 10 Final Mix Final mix & visual lock
Dec 11 - 16 Completion Final mix completion
By Dec 18 Master Ready Final copy ready
Dec 25 Release Theatrical release

CSK Movie

Production Timeline

Timeline Phase Details
Dec 15 Puja Ceremony Before Margazhi month
Dec 30 - Jan 12 Local Shooting Chennai & Rameshwaram shooting - 14 days
Jan 19 - 21 Travel Director, DOP, Producer, Art Director, EP team
Jan 22 - Mar 2 Abroad Shoot 40 days continuous shoot in Australia
📍 Note: Australia chosen as it's summer season (Jan-Mar)
Mar 3 - 12 Edit Lock Edit lock for dubbing
Mar 13 - 25 Dubbing Full dubbing in multiple theaters
Mar 26 - Apr 3 Final Trimming Lock final footage
Apr 4 - 25 Post-Production Background score, DI, SFX, CG, censor
Apr 26 - May 3 Final Mix Final audio mixing and mastering
May 7 Master Ready Final copy preparation complete
May 15 Release Theatrical release

Production Overview

2
Movies in Production
80
Total Shooting Days
5
Months Timeline
Dec-May
Release Window